Southport Levee Improvement Project Road Closures

Southport Levee Project workers

New traffic control measures will be temporarily installed beginning Monday, August 28, along South River Road between Locks Drive and Linden Road for tree removal work along the levee. During this period, Sacramento Yacht Club and Sherwood Marina can be accessed via Linden Road. Village Parkway can be used as an alternate route through the project area.

South River Road Closed from Linden Road – Village Parkway

Linden Road Closed Permanently

The Southport Levee Improvement Project involves the construction of flood risk-reduction measures along the Sacramento River South Levee as required by the state.

Earthwork along the setback levee will continue into the fall.

 

 

This entry was posted in City Projects, Flood Protection and tagged , , , , , , . | Bookmark the permalink.