Washington District Infrastructure Project Update 2/1

SCHEDULE FOR THE NEXT TWO WEEKS 

Grand Gateway
• Begin joint trench work on Tower Bridge Gateway, starting from 5th Street working toward 7th Street. This will result in minor traffic impacts of lane and shoulder closures.

Washington District
• Begin installing 8” sewer line on the south side of C Street (between 4th and 5th Streets), as well as on 4th Street (between C Street and the RR tracks). This work will require lane closures and short detours.
• Begin installing 12” sewer line on E Street, starting from the 6th Street intersection working eastward. This work will require lane closures and short detours.
• Continue potholing utilities in F and G streets, as well as 8th street.
• Test newly installed 8” water line at B Street and 2nd Street, and tie in to existing water system. Residents and businesses will continue to be notified of water shutdown dates and times to accommodate this tie-in.
• Grade curb/gutter & driveways on 6th Street.
• Preparing for sewer bypass on F Street.

Washington District trench digging

PROJECT IMPROVEMENT DETAILS:
Grand Gateway
• New 7th Street Segment (West Capitol Avenue to Tower Bridge Gateway)
• New signalized Tower Bridge Gateway – 7th Street intersection
• New Transit / Streetcar Stop on westbound Tower Bridge Gateway
• Signal removal and modification at West Capitol Avenue & 5th Street intersection
• Two-way separated bicycle path along West Capitol Avenue (Grand Street to 5th Street)
• Convert West Capitol Avenue auto segment to one-way (eastbound) for traffic

Washington District
• Wider sidewalks, street lights, landscaping, way-finding and public art on E Street (5th Street to 3rd Street)
• Bike lanes, wider sidewalks, street lights and landscaping on F Street (5th Street to 3rd Street)
• Road resurfacing along 5th Street
• Add 3,200 LF of water mains
• Replace 3,200 LF of storm drain
• Replace 5,500 LF of sewer mains

WORK COMPLETED TO DATE:
Grand Gateway
• All major clearing activities are complete.
• Deactivation of utilities to allow for the construction improvements on Tower Bridge Gateway, West Capitol Avenue, the new segment of 7th Street, and the new 7th Street Parking Lot is complete.

Washington District
• All major clearing activities are complete.
• Added 550 LF of water main
• Replaced 850 LF of storm drain
• Replace 1,000 LF of sewer main

About

The City of West Sacramento commenced construction of the Grand Gateway / Washington District Infrastructure Project on November 13, 2017. The project will add a new segment of 7th Street connecting West Capitol Avenue to Tower Bridge Gateway and a new traffic signal at the Tower Bridge Gateway – 7th Street intersection. It will also create a Grand Gateway entrance to the City core where the Bridge District, Washington District and Downtown converge. In addition, the project will add and replace over 10,000 lineal feet of storm drain, water and sewer mains to facilitate development in the historic Washington District. Multi-modal transportation improvements will incorporate way-finding and public art to the Riverfront and will better accommodate transit, bicycles, pedestrians and automobiles.